Global Change effect on filtered activities

Morne BeeslaarMember for 17 years 3 months
Created
1
12
0
Hi guys,

Help with a quick question will be appreciated.

I am working on a procurement schedule and want to reset some dates. The easiest way is to filter out these activities and then do a global change to reset the activity status to "not started" My question is, will the global change only reset my filtered activities or will it reset all of the activities?

Thanks

Morne

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Hi Morne,
    No it will not affect all activities and do only on filtered activities. If you want to be sure use filter criteria on Global Change.