Importing MSP into P6.1
In the Open Standard
Nathan BurmanMember for 18 years 10 months
- Created
- 3
0
I am having trouble importing and MSP project into P6.1.
I have definitely successfully imported MSP before so am a little confused as the problems seem to be at the MSP end.
When I begin the import process its runs as expected but then MSP opens in the background and the following error message appears
"Cannot save project
Microsoft Office Project does not support saving projects into ODBC, MPD, or MDB formats. Please save the file in a format that is supported by Project"
Does anyone know why this is happening now and not previously? Or is there a P6.1 setting that I have changed that has created an incompatibility issue?
Your help will be greatly appreciated.
I have definitely successfully imported MSP before so am a little confused as the problems seem to be at the MSP end.
When I begin the import process its runs as expected but then MSP opens in the background and the following error message appears
"Cannot save project
Microsoft Office Project does not support saving projects into ODBC, MPD, or MDB formats. Please save the file in a format that is supported by Project"
Does anyone know why this is happening now and not previously? Or is there a P6.1 setting that I have changed that has created an incompatibility issue?
Your help will be greatly appreciated.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?