Skip to content

% complete type

Kumar SMember for 16 years 8 months
Created
2
1
0
dear guys,

i wanted to know
how to change the % complete type for all the acitivities at once.
i was able to change the duration type but the % complete type is not showing in the columns.
so where this can be changed......

thank you,

2 replies

Oldest first
  1. 0
    Andrew Dick ·
    Kumar,
    The column is called ’percent complete type’.

    You can do this through global change;
    Where all of the following = ’Blank’, then ’Percent Complete Type’ = Duration, Physical or Units percent complete.

    Andy
  2. 0
    Kumar S ·
    THANK YOU

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?