Problem in P5 when i change "Data Date"
In the Open Standard
Vasilis KastritsisMember for 19 years 1 month
- Created
- 3
- 2
0
Hello,
Im having the following problems when i try to update the activities in my time schedule and when i try to change the data date.
Here are the steps i am following to update my time schedule.
1) in the status box of each activity i enter the actual start and finish dates (in my case most of them remain the same as planned).
2) then when i run schedule (F9) inserting the current data date the program completely changes the actual dates i entered in the columns while in the gantt chart the bars are in the correct actual dates.
any suggestions to fix this problem?
please let me know! many thanks in advance!
Im having the following problems when i try to update the activities in my time schedule and when i try to change the data date.
Here are the steps i am following to update my time schedule.
1) in the status box of each activity i enter the actual start and finish dates (in my case most of them remain the same as planned).
2) then when i run schedule (F9) inserting the current data date the program completely changes the actual dates i entered in the columns while in the gantt chart the bars are in the correct actual dates.
any suggestions to fix this problem?
please let me know! many thanks in advance!
3 replies
Oldest firstLog in or join to reply