Skip to content

Predecessors finish column

Christian ViddalMember for 17 years
Created
2
2
0
Hi,

Is there any way to include a column where I can see if the precedessors are finished or not? The predecessor column available only shows the activity id.

Reason why I am asking is that we work in excel for gathering progress and it would have been useful to see if predecessors are finished or not.

2 replies

Oldest first
  1. 0
    Balaji Surendiran ·
    hi Christian,

    You can include ’Activity status’ column in the relationship tab which shows the status of the activity..

    Regards,
    Balaji
  2. 0
    Christian Viddal ·
    Thanks Balaji.

    Maybe I did not explain well enough.

    Say I export 1 month look-ahead to excel and distribute for gathering progress and updates. When considering one acitivity, for example A1010, I want to see the predecessors and if the predecessor is completed or not on the same line in excel. This is only for making it simpler for the engineers to understand if the depending work of A1010 is already done. I as a planner can of course see everything in primavera but I need the same information in the excel sheet I use.

    By including the activity status I only see if activity A1010 is completed but not if the predecessor A1000 is completed. Correct me if I am wrong.

    Is there a column similar to include for activity status for predecessors?

    Hope this made sense.
    Appreciate your support.

    Thanks
    Christian

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?