Here we go....After I set a baseline and begin to excute the schedule we have FCO’s (field change orders) issued which add extra manhours to the schedule. How can I enter these hours without affecting my Planned Baseline hours.
I run a report which shows Original Hours, FCO hours, and Hours to Completion. I need this report to show the FCO hours added to the Completion column.

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Vaughn,
    You can use Resource Code or Activity Code or UDF to identify Original Hours and FCO hours and group & sort by those codes you selected to use.

    Another approach is using a separate WBS for FCO activity.