Adding Manhours after Baseline is Set
In the Open Standard
Vaughn EdwardsMember for 18 years 5 months
- Created
- 1
- 3
0
Here we go....After I set a baseline and begin to excute the schedule we have FCO’s (field change orders) issued which add extra manhours to the schedule. How can I enter these hours without affecting my Planned Baseline hours.
I run a report which shows Original Hours, FCO hours, and Hours to Completion. I need this report to show the FCO hours added to the Completion column.
I run a report which shows Original Hours, FCO hours, and Hours to Completion. I need this report to show the FCO hours added to the Completion column.
1 reply