Remaing & Original Durations
In the Open Standard
Jatinder KUMARMember for 16 years 7 months
- Created
- 7
- 1
0
Hi,
I have two calendars in schedule
1)standard 5 Day/week with 8Hrs/Day Calendar.
2)24X 7 Calendar with 24Hrs in day.
If I change calendar from standard to 24X7.It multilies remaining and original duration by app. 4.2 times.
To me it should have changed duration from working days to Calendar day only.
Any comments???
I have two calendars in schedule
1)standard 5 Day/week with 8Hrs/Day Calendar.
2)24X 7 Calendar with 24Hrs in day.
If I change calendar from standard to 24X7.It multilies remaining and original duration by app. 4.2 times.
To me it should have changed duration from working days to Calendar day only.
Any comments???