Cannot change Original Duration in P6 2.0
- Created
- 9
- 4
Hello Planners,
my customer is facing a strange behavior in P6 V2.0:
she's trying to change the duration of some "Task dependant" activities, no resource loaded; she enters a new figure in the Original Duration field of the Activity Detail, Status tab, and the Finish Date does not change, should she re-schedule the project or not.
one more point: the project is not baselined (and the primary baseline bar shows the current project), but the primary baseline bar is displayed; when the customer enters a new duration for a task, the "baseline" bar becomes longer although the "current project" bar does not change.
Any idea? Thanks you all,
Alexandre
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?
