Skip to content

Remaining Units/time

Shah Syed ZaheerMember for 16 years 9 months
Created
2
5
0
Dear All,
If you could tell how this calculation is.
If default units/time is 8/d
calander is 6x8HR.
then suppose there are activities as below.
Activity Duratn BudgetedUnits ActualUni RemainingUnit/time
Marking 02 16 16 16
Excavatn 4 32 32 32
Piping 10 320 320 32
Concrete 02 160 160 80
Columns
upto Glvl 25 800 800 32
The first marking activity default units/time is multiplied but other activities how are the budgeted units, actual units and especially remaining units /time values coming when there is only one single resource assigned with default units/time is 8/d.
thanks in advance.

2 replies

Oldest first
  1. 0
    Shazia khan ·
    Hi-Shahab,

    note that,

    units/time * od= Budgeted Units.


    cal. 6 days per week 8 hr per day,

    please check your cal time prieod


    8 hr /day 6* 8 =48 hr / week and 26 *8 = per months and 26*12 = / years make this correct setting and also check

    your local holy day cal. and correct working time for per year.

    check your Global which cal you are using this must be tick,

    Budgeted units calculated based on activity
    duration.

    if you have 16 ,16 mean 1 resource assign to this activity and duration is 2 days, 2 * 8 = 16 same as 32 means 1 resource assign for this activity and original duration is 4 days 4 *8 = 32 units where as 8 is the unit/time and 4 is your activity original duration.

    Hope it is work for you.

  2. 0
    Shah Syed Zaheer ·
    Ask , Shazia Khan,
    Ramadaan Kareem,
    Original Duration*Default Hrs=Budgeted units
    But it is changing for other activities.
    Piping OD=10 BU=320 AU=320 and Remaining Units/time=32
    Concrete OD=15 BU=480 AU=480 and Remaining Units/time=32
    Only few of the activities have completed not all and only one common resource with default units is 8 hrs/day
    How is the BU and AU and Ru/t getting changed.
    Thanks in advance.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?