Remaining Units/time
In the Open Standard
Shah Syed ZaheerMember for 16 years 9 months
- Created
- 2
- 5
0
Dear All,
If you could tell how this calculation is.
If default units/time is 8/d
calander is 6x8HR.
then suppose there are activities as below.
Activity Duratn BudgetedUnits ActualUni RemainingUnit/time
Marking 02 16 16 16
Excavatn 4 32 32 32
Piping 10 320 320 32
Concrete 02 160 160 80
Columns
upto Glvl 25 800 800 32
The first marking activity default units/time is multiplied but other activities how are the budgeted units, actual units and especially remaining units /time values coming when there is only one single resource assigned with default units/time is 8/d.
thanks in advance.
If you could tell how this calculation is.
If default units/time is 8/d
calander is 6x8HR.
then suppose there are activities as below.
Activity Duratn BudgetedUnits ActualUni RemainingUnit/time
Marking 02 16 16 16
Excavatn 4 32 32 32
Piping 10 320 320 32
Concrete 02 160 160 80
Columns
upto Glvl 25 800 800 32
The first marking activity default units/time is multiplied but other activities how are the budgeted units, actual units and especially remaining units /time values coming when there is only one single resource assigned with default units/time is 8/d.
thanks in advance.
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?