Updating Schdule
In the Open Standard
Ariel MalibiranMember for 17 years 7 months
- Created
- 3
- 1
0
guys’ help please..
during the monthly update on my schedule using Primavera 6 ver 7, I tried to compare 3 schedules:
1. the first is the current schedule( the updated one, say for the month of July, 2010),
2. second is the original schedule which I assigned as the primary baseline and,
3. the third is the updated schdule for the month of June 2010 which I assigned as the secondary baseline..
When i showed all the bars, I noticed that all the activity bars for the secondary baseline (which is the June 2010 updated schedule)starts as per the actual start date of the in-progress/completed activities or the early start for non-starting activities and uses the duration to calculate the finish date..
How is this possible and how can I show the secondary baseline bars reflecting the "true bars" of the schedule on june 2010 update.
during the monthly update on my schedule using Primavera 6 ver 7, I tried to compare 3 schedules:
1. the first is the current schedule( the updated one, say for the month of July, 2010),
2. second is the original schedule which I assigned as the primary baseline and,
3. the third is the updated schdule for the month of June 2010 which I assigned as the secondary baseline..
When i showed all the bars, I noticed that all the activity bars for the secondary baseline (which is the June 2010 updated schedule)starts as per the actual start date of the in-progress/completed activities or the early start for non-starting activities and uses the duration to calculate the finish date..
How is this possible and how can I show the secondary baseline bars reflecting the "true bars" of the schedule on june 2010 update.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?