Skip to content

Updating Schdule

Ariel MalibiranMember for 17 years 7 months
Created
3
1
0
guys’ help please..

during the monthly update on my schedule using Primavera 6 ver 7, I tried to compare 3 schedules:
1. the first is the current schedule( the updated one, say for the month of July, 2010),
2. second is the original schedule which I assigned as the primary baseline and,
3. the third is the updated schdule for the month of June 2010 which I assigned as the secondary baseline..

When i showed all the bars, I noticed that all the activity bars for the secondary baseline (which is the June 2010 updated schedule)starts as per the actual start date of the in-progress/completed activities or the early start for non-starting activities and uses the duration to calculate the finish date..

How is this possible and how can I show the secondary baseline bars reflecting the "true bars" of the schedule on june 2010 update.

3 replies

Oldest first
  1. 0
    Ariel Malibiran ·
    this is in addition to post:

    When i showed all the bars, I noticed that all the activity bars for the secondary baseline (which is the June 2010 updated schedule)starts as per the actual start date of the in-progress/completed activities or the early start for non-starting activities and uses the duration to calculate the finish date..

    should be:

    When i showed all the bars, I noticed that all the activity bars for the secondary baseline (which is the June 2010 updated schedule)starts as per the actual start date of the in-progress/completed activities or the early start for non-starting activities and uses the duration to calculate the finish date.thus the end date for the completed/in progress activities has been superseded..to make it clearer i’ll put it this way: say an activity originally has 6 days duration and actual start on june 7 2010 and actual finish is june 17 2010 ( 10 days due to some delays) the bar that will be shown is from june 7 to june 12, 2010 and not from june 7 to june 17 2010.that makes it shorter and contrary than what has happened in the actual...

    How is this possible and how can I show the secondary baseline bars reflecting the "true bars" of the schedule on june 2010 update.

    thanks
  2. 0
    Rodel Marasigan ·
    Ariel,
    Baseline use planned date and not actual dates. Below link are some insights on how to set baseline for your reference
    How to set Baseline- After revised the Schedule and to Post #2
  3. 0
    Ariel Malibiran ·
    Thanks Mr Rodel..the link you have provided is the perfect solution to my query so i can compare the bars for the 3 schedules.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?