How to show nonwork time(neck) in collapsed bar

Kinnar PatelMember for 20 years 4 months
Created
3
3
0
Hi everyone,
Does anyone know that how to show neck in collapsed bar.
Thanks in advance.
Regards,
Kinnar

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Kinnar,

    View-> Bars and under Bar Settings tab mark the Bar necking required and if mark Show Bar when collapse on Group Band settings as shown below.
    Bar Necking
  2. 0
    Kinnar Patel ·
    Hi Rodel,
    Thanks very much for reply.
    It can show neck in the bar when its not collapsed.
    I wanted to show it on the bar even when it collased.
    Like, 1 WBS have 4 actvities. When you collapsed it, shows 4 diffrent bars in a same line. I want to show neck on those collapsed bars.
    Thanks.
    Kind Regards,
    Kinnar
  3. 0
    Rodel Marasigan ·
    Kinnar,
    P6 don’t support necking on summary band. The work around is to create a WBS Summary Task and apply the necking then filter only WBS Summary Task as sample below:
    Bar Necking Summary