BL 1 Start Dates Slip once we assign actual start

Izam ZakariaMember for 20 years 4 months
Created
1
2
0
Guys,

As subjected above, I had problem when I did assign actual start, the BL Start dates will change accordingly.

But this not happen to BL Finish when actual finish had been assigned.

What setting I should do guys?

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Izam,
    When actual start has been tick and data date move the Baseline will slip if the remaining duration was not change. You need to adjust remaining duration to keep the planned finished date if progress was as planned.