Start Date Problem with Finish to Start Relationship

Robert McGheeMember for 18 years 6 months
Created
1
1
0
I have a predecessor activity 65% complete with a finish date of September 13, but the successor activity with a finish-to start relationship shows a start date of September 13 after I "schedule". Each has a "physical" percent complete type and there are no lags in the relationship. Never had this happen before so am looking for some insight.

Thanks,
Robert McGhee

1 reply

Oldest first
  1. 0
    Shareef Abdul Azeez ·
    Hi Robert

    Check the time format...

    Include minutes and check ....!!!