Calculation Error
In the Open Standard
Comert VardarMember for 16 years 1 month
- Created
- 4
- 2
0
Hello my friends,
I wonder why my already defined and assigned resources budgeted costs always produce 1 digit more than usual.
for example; i assigned 1 Excavator with default and max. units; 10h/d
lets say price; 55$/h
and activity duration; 100d
so normally bugdeted cost must be ; 10*55*100=55.000$ but
it shows 550.000 for all kind of resources assigned. i think there are some calculation options problems rather than errors.
could you please help me with overcoming this sick problem.?
thanks all the way,
Comert Vardar
I wonder why my already defined and assigned resources budgeted costs always produce 1 digit more than usual.
for example; i assigned 1 Excavator with default and max. units; 10h/d
lets say price; 55$/h
and activity duration; 100d
so normally bugdeted cost must be ; 10*55*100=55.000$ but
it shows 550.000 for all kind of resources assigned. i think there are some calculation options problems rather than errors.
could you please help me with overcoming this sick problem.?
thanks all the way,
Comert Vardar
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?