the count of activities is different?

Niles LuoMember for 20 years 11 months
Created
1
11
0
hi, everyone
the count of activites is different between the project is opened and closed in P6v7. Any information is appreciate.
Best Regards.

1 reply

Oldest first
  1. 0
    David Kelly ·
    The value shown when the project is closed is as of the last summary run. Check "Tools: Summarize"

Log in or join to reply