Budget At Completion in Projects View---Varying
In the Open Standard
Shareef Abdul AzeezMember for 21 years
- Created
- 2
- 1
0
Hello friends
I created a sample project in P6 with a Budgeted Total Cost of $230,500.
Now when I go to the Projects View (Enterprise -> Projects), the Budget At Completion is $230,500. Everything all right till here.
As soon as I close this project or open another project from the Project view, the Budget At Completion in the Project view (for the same sample project) changes from $230,500 to $180,500.
Any idea whats happening??
I created a sample project in P6 with a Budgeted Total Cost of $230,500.
Now when I go to the Projects View (Enterprise -> Projects), the Budget At Completion is $230,500. Everything all right till here.
As soon as I close this project or open another project from the Project view, the Budget At Completion in the Project view (for the same sample project) changes from $230,500 to $180,500.
Any idea whats happening??
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?