Budgeted Unit for "Cash" resource

James bidMember for 17 years 1 month
Created
4
18
0
Hi Guys!

I just want to know if there is a rule of thumb in computing the budgeted units for the CASH resource in each activity?

Thanks in advance.

Chris

4 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Christopher,
    What do you mean by rule of thumb in computing budgeted units for CASH resource? P6 defaults is duration * hours per unit when assigning resources.

    The rule of thumbs is a guess estimate (based on experience) of how many resources will work for each activity.

    Ex: Excavation: (manual)
    Labor: labor/cum

    Excavation: (machine)
    Labor: Operator/cum
    Machine: Excavator hrs/cum

    Depending on location, country and soil components - norms plus contingencies can be used.
  2. 0
    James bid ·
    Thanks Rodel for the reply.
    Here is the resource of one activity that I derived from the program .




    RC-08 Resource and Role Assignments
    Activity Name
    Resource ID Name Cost Account Budgeted Units % Complete
    CMCSMLC50 CMCSMLC50 Site Preparation Area 0
    D001LB.Labor 1792
    D002GA.Ganger 168
    D015HVO.Heavy Vehicle Operator 700
    P002GR.Grader 224
    P004WL.Wheel Loader 224
    P009TR4.Truck - 40 m3 112

    D003CA.Carpenter 224
    D04MA.Mason 112
    P007JCB.JCB 56
    P014HB.Hiab 4 X 2 Truck 28
    Cash.Cash 12208000
  3. 0
    Rodel Marasigan ·
    Christopher,
    It seems that your resources as assigned to cost account and taken from the estimate. What is the problem with that and what is your query?
  4. 0
    James bid ·
    Hi Rodel?

    My query is about the budgeted unit for Resource " Cash.cash 12208000", is there a standard in calculating the budgeted unit for this?.

    I’m just curious on how to calculate.

    Thanks