Skip to content

Budgeted Unit for "Cash" resource

James bidMember for 17 years
Created
4
1
0
Hi Guys!

I just want to know if there is a rule of thumb in computing the budgeted units for the CASH resource in each activity?

Thanks in advance.

Chris

4 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Christopher,
    What do you mean by rule of thumb in computing budgeted units for CASH resource? P6 defaults is duration * hours per unit when assigning resources.

    The rule of thumbs is a guess estimate (based on experience) of how many resources will work for each activity.

    Ex: Excavation: (manual)
    Labor: labor/cum

    Excavation: (machine)
    Labor: Operator/cum
    Machine: Excavator hrs/cum

    Depending on location, country and soil components - norms plus contingencies can be used.
  2. 0
    James bid ·
    Thanks Rodel for the reply.
    Here is the resource of one activity that I derived from the program .




    RC-08 Resource and Role Assignments
    Activity Name
    Resource ID Name Cost Account Budgeted Units % Complete
    CMCSMLC50 CMCSMLC50 Site Preparation Area 0
    D001LB.Labor 1792
    D002GA.Ganger 168
    D015HVO.Heavy Vehicle Operator 700
    P002GR.Grader 224
    P004WL.Wheel Loader 224
    P009TR4.Truck - 40 m3 112

    D003CA.Carpenter 224
    D04MA.Mason 112
    P007JCB.JCB 56
    P014HB.Hiab 4 X 2 Truck 28
    Cash.Cash 12208000
  3. 0
    Rodel Marasigan ·
    Christopher,
    It seems that your resources as assigned to cost account and taken from the estimate. What is the problem with that and what is your query?
  4. 0
    James bid ·
    Hi Rodel?

    My query is about the budgeted unit for Resource " Cash.cash 12208000", is there a standard in calculating the budgeted unit for this?.

    I’m just curious on how to calculate.

    Thanks

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?