is there anything wrong with p6 v7

Rola SabbahMember for 16 years 10 months
Created
3
2
0
Hi every body
I’m using p6 v7, and its doing some weird things, when i change the relationship and then schedule the activity stays with the first date and there is no constraints.
I even deleted the preedecc. of an activity and pressed F9 the start datet was not the data date, it was the date before deleting the predec.
Any ideas????????????

3 replies

Oldest first
  1. 0
    Gary Whitehead ·
    I’m sure you’ve checked this, but has the activity got an actual start date?
  2. 0
    Niles Luo ·
    hi,
    pls check that this activity does not have relationship from other project.
    Best Regards,
  3. 0
    Gene Beam ·

    Check and clear External Early Start and Finish

    I came across this a few months ago and I found that when you copy and past some activities they bring across dates in the fields called External Early Start and External Early Finish. I think this was because I was copying completed activities. Just clear any dates if the External Early Start and External Early Finish.