Physical % complete

Kim KingMember for 16 years 1 month
Created
4
2
0
I’m using physical % complete to progress my plan, but when I roll up, there is no overall percentage at the top of any of my levels, does anyone know how to get this to show up???

Thanks

4 replies

Oldest first
  1. 0
    Oliver Melling ·
    Try using a different column to display the % complete.

    Such Performance % Complete
  2. 0
    Shazia khan ·

    kim,   Physical % rolled up

    kim,

     

    Physical % rolled up to WBS Level-1 is not worked in P6 as of now, may be next version we will have this option,

     

    so you may chose other option. Performance Complte nad schedule % complate ,so on.

  3. 0
    Sajeeth Sukumaran ·

    You could try for Duration % Complete.

    P3 also uses the same criteria to show the overall %

    --------

    Regards,

    Sajeeth

  4. 0
    Sajeeth Sukumaran ·

    You could try for Duration % Complete.

    P3 also uses the same criteria to show the overall %

    --------

    Regards,

    Sajeeth