Start Milestone FS Task Dependent Activity (Date problem)
In the Open Standard
Ruben LopezMember for 16 years 1 month
- Created
- 2
- 3
0
HELP!
Well I thought this problem was taken care of in P6.7, but so far I’m not seeing it. I have a START MILESTONE tied to an activity by way of (FS). My milestone start on 9/15 and its successor should on 9/16, but instead it start on the same day. I’ve even gone under user preferences and set my DATE TIME to show minutes (12 hour) and adjusted the constrained milestone to start at the last minute of my 10 hr work day. Still, no luck.