Acknowledging the new dates after Resource Leveling
In the Open Standard
Ijaz AhmadMember for 20 years 3 months
- Created
- 2
- 1
0
Hello Guys,
I leveled the resources and the resource profile to me looks fine. I want to acknowledge the leveled dates but the problem is when I hit schedule, the dates go back to previous settings, even after I have unchecked the "Preserved scheduled early and late dates" option under level resources dialog box.
Any help will be highly appreciated.
Thanks
Ijaz
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?