Hello Guys,

I leveled the resources and the resource profile to me looks fine. I want to acknowledge the leveled dates but the problem is when I hit schedule, the dates go back to previous settings, even after I have unchecked the "Preserved scheduled early and late dates" option under level resources dialog box.

Any help will be highly appreciated.

Thanks

Ijaz

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Ahmad,when you hit F9 after

    Ahmad,

    when you hit F9 after your project has been resource-leveled, P6 reschedule the project based on links between activities and date constraints; this means you will lose the result of leveling

    to acknowledge the result of leveling, change the links between activities to take into account the new start dates of the activities based on the resource availability

    Alexandre

  2. 0
    Satish Kumar ·

    Reschedule with resource leveling option

    Hi

    when you click the resource leveling icon There is a check box option in the pop up window which states to consider scheduling with resource leveling.

    cheers

    K