How to add a resource to all activites

Sajid SyedMember for 18 years 8 months
Created
3
2
0

many of the activities in my plan have resources added to them.  Now have created a new resource and i want to add this to every activity as 1 per unit time.

 

Is there any way to do this in one go without having to add it individually to all activities

3 replies

Oldest first
  1. 0
    Mahmoud Amin ·

    (Global Change)

    Hi Sayed,

    did u try the (Global Change) tool?

  2. 0
    Eric Rivera ·

    Hello, Sajid! Select the

    Hello, Sajid!

    Select the FIRST activity you want to add the new resource to.

    From the RESOURCE tab, click the ADD RESOURCE button to open the ASSIGN RESOURCES dialog box.

    Go back to your list of activities and select the multiple activities (Shift-click or CTRL-click) that you want to add the new resource to.

    Go back to the ASSIGN RESOURCES dialog box and select the new resource you want to add to all the selected activities.

    Click the ASSIGN button (Green +).

    The new resource should be assigned to all the activities you have selected.

     (NOT sure about the 1 per unit time, though...)

    ENJOY!

    Eric

  3. 0
    Shareef Abdul Azeez ·

    HiI do not think Global

    Hi

    I do not think Global Change could help !!!!

     

    Best would be Import Export using SDK

     

    It looks like there is one more way---- I found this in the P6/P5 forum topic: P6 Tips & Tricks.....

    "it is easier to first select all the activities (using shifht or ctrl) and then select the resource from the resource assignment window...
    p.s the select bottom will be disabled when choosing more than one activity, hence, press on the resource icon on the right menu
    same for activity codes, roles etc...."

     

    Eric has already mentioned...but I didnt see

     

    Best Regards

    Shareef A Azeez