What is new in PRIMAVERA P6 Version 7?

Naveen PaladuguMember for 16 years 3 months
Created
3
5
0

Dear all

              I would like to have some information form you regarding changes/up-gradations in P6 version7 to its lower versions. Recently, my company PC has been installed with P6.7. So information regarding this will be extremely helpful.

3 replies

Oldest first
  1. 0
    Naveen Paladugu ·

    In continuation with the

    In continuation with the above subject, here, I am giving some that I have been found in P6 Version 7. Please correct me If any thing to corrected or added. And please add new points.

    1) Progress line has been added. It displays progress with respect to data date in bar chart area. 

    2)Re-numbering of activity Ids.

    3)Planned start & Planned finish columns has been added.

  2. 0
    David Johnstone ·

    One of the most awaited

    One of the most awaited "enhancements" is that way you can now show durations in days based on the individual task calendar.

    You will first need to set-up each Calendar, and ensure you specify what a day;week;month;year represent in hours. These settings are then used to "calculate" what a "day" is when you choose to show your durations in days rather than hours.

    Version 7 still has a few "flaws," one being the roll-up or summary of TF values.

    Setting the height of activity bars is still done by choosing between "thick,thin,skinny" bars if you are using the Windows Client.

    Ask your vendor for information on any other enhancements...

    Have fun!

  3. 0
    Naveen Paladugu ·

    Mr. David. Thank you  for

    Mr. David. Thank you  for your informative reply. Could please explain what is wrong in summary of TF values.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?