P6 Roll-up (Performance % CompletE)

Craig FreakeMember for 21 years
Created
3
2
0

Hi All,

In p6, is there any way to roll-up % complete as based on Performance? In my schedule program, some activities are costed/resourced, however,  there is a Owner review period withtout respective costing.... Anayway P6 can roll progress based on a group of activities summarized by WBS? S

 

cenario 1, 6 activities with no resources and only half are complete, what is the base approach to get a summary of progress which ties as close as possible to EVM philsophy??

 

Much appreciate your advice...

3 replies

Oldest first
  1. 0
    Craig Freake ·

    Nobody can help??? Or is is

    Nobody can help??? Or is is just not possible in P6 to roll-up to perfomance % complete without adding cost/resource to any activity??? Want to stay away from Duration % complete...... Much appreciate your suggestions..thanks

  2. 0
    Shareef Abdul Azeez ·

    Hi Craige Check out these

    Hi Craige

     

    Check out these forum threads. They have the answers you are looking for

     

    http://www.planningplanet.com/forums/primavera-version-pm5-pm6/418053/schedule-perforemanc-complete-roll

     

    http://www.planningplanet.com/forums/primavera-version-pm5-pm6/420413/performance-complete-vs-schedule-complete

     

     

    Best regards

    Shareef A Azeez

  3. 0
    Craig Freake ·

    Thanks Shareef!!! WIll try

    Thanks Shareef!!! WIll try it..