Negative actual labor units in P6

Ayo AnifowosheMember for 16 years
Created
0
3
0

My P6 project is set up with Labor Resources , each activities have budgeted labor unit .

Each labor have access tp P6 timesheet , so every week i dowload the actual units(hrs) booked against each activities in to my primavera plan from P6 timesheet.

what i get most of the time now is negative actual units(hrs).

i dont understand why i will be importing negative units from P6 timesheets , when i check the timesheets from P6Timesheets  i see positive values.

can someone help?