How to choise the général method of the planning (Fixed unit or Fixed duration or physical ... Top down method ...)

walid LahianiMember for 15 years 11 months
Created
3
2
0

 

Good morning,

We have a project ( Construction of LNG train in Balhaf for example) with many Sub contractors ,....,many plannings,.

How to proceed to prépare the Master planning ,what are the steps to follow...

Which calculation méthod to use ,the type of the activities,....

 

Thank you

 

3 replies

Oldest first
  1. 0
    walid Lahiani ·

    May be you have to choice

     

    May be you have to choice the Step méthod

  2. 0
    Shazia khan ·

    first you determine your self

    first you determine your self , how you want to update your project,

    is that schedule have fixed resource or fixed duration.

    best practice is herego

    1- duration type       ===== fixed duration and unit

     

    2-Percent type       ====== Duration for engineering & procurement activity,

                                               Physical for construction activity.

     

    3-Activity type ==========  Task Dependent ,  ( for mile stone depends start MS or Finish MS )

     

    with this setting you need to update your schedule based on your physical judgement or progress measurement sheet,

    update with Phy %  value , remaining duration,  start date , etc,

    resource update actual unit and remaining units..

  3. 0
    walid Lahiani ·

    Thank you for your

    Thank you for your explication,

     

    "If we don't know the method of calculation ,we can not work properly"

    It's like the foundation of the building

     

Log in or join to reply