How to add 50 labours to one activity?

walid LahianiMember for 15 years 11 months
Created
1
2
0

Hello

Imagine we have a task which original duration equal to 7 days

one labour work 10h/day

If I add this labour to the activity the Budget unit become 70=10h*7days

If I want  50 labours working on this activity I have to change the budget unit to 10hx7daysx50labours=3500 isn't it?

Thank you

1 reply

Oldest first
  1. 0
    Niles Luo ·

    hi,   I think it is. Best

    hi,

      I think it is.

    Best Regards.