How to add 50 labours to one activity?
In the Open Standard
walid LahianiMember for 15 years 11 months
- Created
- 1
- 2
0
Hello
Imagine we have a task which original duration equal to 7 days
one labour work 10h/day
If I add this labour to the activity the Budget unit become 70=10h*7days
If I want 50 labours working on this activity I have to change the budget unit to 10hx7daysx50labours=3500 isn't it?
Thank you