Skip to content

Different between P3 & P6 in update ???

Jehad Aldaoud PMP, PMI-SPMember for 16 years
Created
1
2
0

Hello all, how are you 

I faced problem when i doing update for schedule, my problem is when I put progress data in schedule but in (P3) i had total float = -10 , but when put the same data on schedule (P6) , i have total float = -5, the base schedule was on (P3) and convert it to (P6), i think it must total float the same in P3 & P6 , the schedule is the same 

 

please advice 

1 reply

Oldest first
  1. 0
    David Kelly ·

    There are calendar

    There are calendar differences in the two systems - check those. Also check the calendar used for summary durations. in P6 upto version 2.1 it is the project default calendar, NOT the project calendar

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?