using different type of % complete for the same project

Kumar SMember for 16 years 8 months
Created
4
2
0

Dear all

i have a query regarding the % complete type for the activities

i have to  use the units % complete for 60% of activities (these activites are totally dependent on the resourceas available)

around 20% activities are based on the duration type(here resources does not matter only duration counts)

around 10% activities are dased on physical % complete(the actitites should be assessed by the % scope finished)

SO IF I USE these three % complete type in a single project what should be my settings while updating the schedule

i wanted to known if the percentages will show correctly when it is rolled up to the wbs level.

please guide me

 

thanks in advance

 

 

 

4 replies

Oldest first
  1. 0
    Amit Parmar (PMP) ·

    Hi,Primavera has following

    Hi,

    Primavera has following columns:

    1) Duration % complete

    2)Units % Complete

    3) Physical % complete

    Each of these columns will show you rolled up values in wbs for the respective type of activties. ie. If a WBS has a mix of duration, units & pysical the rolled up values for these activties will be in their columns and you would not get a combined rolled up percent complete.

    In order to get a combined % complete, you have to add column "Performance % complete" which at activity level :

    Performance % Complete = Activity % complete (Activity Level Only)

    In order for the value to roll up to wbs level the project should have a cost loaded baseline assigned to it. Cause WBS level performance % complete is calculated by the following formula

    Performance% Complete = Earned Value/ Budget at Completion

    I know this is confusing so i would suggest tht you make a simplet project with 5 activities of different types and assign cost to it and you would autmoatically see the percent commplete getting rolled up into a percentage.

    Note- If you have weightages fo these activities with you, then i can suggest you an alternate way to get rolled up percentages.

    Regards

    Amit Parmar

  2. 0
    Kumar S ·

    Dear Amit Thank you very much

    Dear Amit

    Thank you very much for your valuable input.

    i will work on it by creating a sample project and analyse it

     

    one more thing i want to know if we can assign weightage to a perticular activity.

    i thought that weightages can be given only at the WBS LEVEL only

  3. 0
    Amit Parmar (PMP) ·

    HI Kumar,You are correct when

    HI Kumar,

    You are correct when you say that the weightages can be assigned only at the wbs level to wbs milestones. But we use a workaround by assigning resources in values on weightages and updating the activities based on that. But it works if only the weighted resource is updating the activity.

    Regards

    Amit

  4. 0
    Kumar S ·

    Dear Amit   thnaks for your

    Dear Amit

     

    thnaks for your reply

    so you mean to say that hte weightages cannot be given to the activities.

    i have a doubt about the Est weight option for the actitities

    what is the use of this. can we not assign the weightages here for a set actitivities which are coming under a  perticular WBS Node.

     

    can you please brief me how can  we assign resources in values on weightages.

     

     

     