How to Update a Baseline with Current Actuals/Progress
In the Open Standard
Edniel RecamadasMember for 17 years 5 months
- Created
- 4
- 3
0
Dear PP'ers,
I've been involved recently at ongoing buildings project (now in 7th month of a 1.5 year contract) and when I compare the update using the Claim Digger in P6 there have been a lot of changes done by the previous planner on the updated schedule.
What's the best way (most reliable) to update the baseline using the current actuals/progress.
Thanks for the assistance,
Edniel
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?