Baseline Late Bar in P6 v 6.2

Ahsan ZiaMember for 18 years 6 months
Created
1
12
0

I have a baseline added in the current schedule. Could anybody tell me how to show the baseline late bar?

1 reply

Oldest first
  1. 0
    Paul Harris ·

    This is one of the many

    This is one of the many issues I have with this software.

    The olny way I have found to display the Baseline Late dates is to create a copy of the schedule and set all tasks to ALAP and then set this schedule as a Baseline.

    Regards

    Paul E Harris

    Directo r

    Eastwood Harris Pty Ltd http://eh.com.au