Importing from P3 to P6 Cost Difference

Ronnel Anthony CelerioMember for 18 years 8 months
Created
0
3
0

Hi All,

 

I Have a small Problem in Importing a Units & Cost Loaded P3 schedule to P6, the cost doesnt seem to match even though All the calculations based on the P3 Software are correct, there seems to be a problem in some Cost decimals when you convert the P3 to P6.

There is no Problem within the Units Value; there is no units Variance, but when you get to the Cost Computations, there is a decimal value difference, what seems to be the problem?

I always use "Recalculating assignment cost using units & prices" when importing using the very same cost, units, price & resource details in P3.

 

Need your Help. Thank you.

 

Regards,

 

Ronnel Anthony Celerio

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?