Skip to content

Budgeted Cost

Rohit KMember for 18 years 5 months
Created
1
2
0

Hi All,

This is relating to the Budgeted Cost (BC). When I scheduled for the first time after entering the labour and price for the activities the BC for only some of the activities were displayed, that too at sometimes only for 1 or 2 resources if I had 4 - 5 resources assigned to that acivity. After some readings and research I inserted the Cost Unit Linked in the Activity Layout ticked for each of the resource for the activity then the BCs were displayed.

Why is this so? Isnt there any default wherein the BCs are displayed without doing this manual procedure?

Any responses to help in this matter will be appreciated by the planners.

Rohit

1 reply

Oldest first
  1. 0
    Ferdinand U. ·

    hiif its the COST

    hi

    if its the COST UNITS LINKED

    you can use global change to replace it to YES or NO (whichever you want)

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?