Skip to content

Why does P6 does not show BL2 % Complete

Haresh JayanthMember for 20 years 1 month
Created
1
1
0

Dear All,

I have assigned two programs as primary baseline and secondary baseline. But i am not able to get the column showing % complete for the secondary baseline program i.e. BL2.

How to solve this problem.

 

Pls do reply.

 

regards,

 

Haresh Jayanth

1 reply

Oldest first
  1. 0
    Michael Ramos ·

    you can try a

    you can try a workaround

    assign your BL2 as project baseline and copy the schedule % to UDF using global change (after shifting the data date)

    then assign BL1 as project baseline and put your BL2 as primary

    now you can compare sched % (BL1) and UDF (BL2)

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?