how P6 computes for total float subtotal and why schedule variance is not zero reference to newly created baseline?

Jerome SorianoMember for 15 years 11 months
Created
5
6
0

Dear PP Members,

1) How does P6 compute for the subtotal of total floats. There is a group consist of 5 activities, 4 activities having total float of 2 days each and 1 activity whose total float = -10days. The group subtotal of total float is -6days.

2) Why schedule variance is not equal to zero reference to a newly created baseline of an "in-progress project''? As far as I know, schedule variance should be zero because the baseline is just the exact copy of the current. Is there a way in P6 to set SV=0?

Thanks in advance.

Merry Christmas!!!

Jerome

 

 

 

5 replies

Oldest first
  1. 0
    Pinan T. ·

    1) Default Global Calendar

    1) Default Global Calendar affects Total Float on Grouping bands summary

    2) No.

  2. 0
    Michael Ramos ·

    TF on summary equals Latest

    TF on summary equals Latest LF minus Latest EF under the wbs code

  3. 0
    Rockzy Sales ·

    Hi, I believe TF = LS - ES or

    Hi,

     

    I believe TF = LS - ES or LF - EF of an activity. In a summary of group of activities, TF (summary) equals the TF of the last activity to start or to finish in the group or WBS as Michael said.

     

    regards,

    the Rock

  4. 0
    Jerome Soriano ·

    Thanks a lot michael. How do

    Thanks a lot michael.

    How do other planning engineers deal with the issue #2 I mentioned above?

     

  5. 0
    Jerome Soriano ·

    '

    '

Log in or join to reply