Longest Path with Mixture of Positive and negative float

Haresh JayanthMember for 20 years 1 month
Created
9
2
0

Dear All,

My program is showing longest path in P6 , with some activties which has a positive float of 135 days also, as well as Zero days float. How could it be possible to generate longest path with positive float and zero float.

Can anybody explain.

regards,

 

Haresh Jayanth - PMP - Planning Manager

 

 

9 replies

Oldest first
  1. 0
    Rockzy Sales ·

    Hi,this is interesting, isn't

    Hi,

    this is interesting, isn't zero float activities should be in the longest path (if this is also the critical path)...

    but for 135 days float? check P6 options...

     

    cheers,

    the Rock

  2. 0
    Haresh Jayanth ·

    Dear Rockzy, The option for

    Dear Rockzy,

    The option for longest path is kept " Total float = 0" , still i am getting longest path with positive float of 136 days also along with 0 days float activity, what would be any other reasons.......

     

    regards,

     

    Haresh Jayanth

  3. 0
    Stefano Bignozzi ·

    Different calendars?

    Different calendars?

  4. 0
    Mike Testro ·

    Hi Haresh When diod you last

    Hi Haresh

    When diod you last reschedule the project?

    Do you have any restraint flags on the tasks?

    Are any tasks set ALAP?

    Does every task have at least one outgoing link?

    And as Stefano says - check your calendars particularly if you have calendars attached to resources.

    Best regards

    Mike Testro

  5. 0
    Gary Whitehead ·

    check for:   project

    check for:

     

    project constraints

    activity constraints

    different calendars

    that you are using the default 'longest path' filter

  6. 0
    Paul Naughton ·

    Are you looking at a longest

    Are you looking at a longest path over multiple projects or a single file?

  7. 0
    Nathaniel Cagara ·

    check activities that have

    check activities that have mandatory constraints.

    total float of activities in a path that leads to a mandatory constrainst are calculated relative to mandatory constraint date and not based on project finish date.

  8. 0
    Kamal Joshi ·

    Its possible to have positive

    Its possible to have positive Float on the activities falling in Critical Path, when there are multiple critical paths on the program. Probably the reason stated ealier on Constraints given on activities or its Critical Successors/ Predecessors OR your activities showing 136 float have Actual Dates fed on.

  9. 0
    Ronald Winter ·

    Haresh,   P3’s version of

    Haresh,

     

    P3’s version of longest path has nothing to do with Total Float.  Only the forward pass calculations are considered.  Once you understand how longest path is calculated, then you will see this fact.  Try a paper of mine at http://ronwinterconsulting.com/published.htm called, “Longest Path Value” for more on this interesting subject.  Good luck!

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?