Skip to content

Performance % complete to be shown as BL1 Column

Haresh JayanthMember for 20 years 1 month
Created
5
1
0

Dear All,

Why dont we have a column to choose Baseline perrformance % complete in P6. How can we get a column to show this ?? Any ideas from any expert.

regards,

 

Haresh Jayanth

5 replies

Oldest first
  1. 0
    Jerome Soriano ·

    i think you want to see the

    i think you want to see the schedule % complete.

    schedule % complete = planned value cost/budgeted cost

     

  2. 0
    Haresh Jayanth ·

    Dear Jerome, I want BL1

    Dear Jerome,

    I want BL1 performance% complete column in the updated program. But P6.7 , doesnt have any provision of having a column as BL1 Performance % complete. The same column can be seen in Updated program i.e. performance % complete. How to get this column , where i can show the planned performance % complete as any given date.

    regards,

     

    Haresh Jayanth

  3. 0
    Pinan T. ·

    hiwhat do you have in

    hi

    what do you have in performance % that is not available in schedule %?

    they are the same

  4. 0
    Jerome Soriano ·

    @ haresh, planned performance

    @ haresh,

    planned performance % complete @ any given date (data date) is the schedule % complete.

    so what you are looking for is exactly the "schedule % complete".

    you can check in your schedule that schedule % complete = planned value cost/baseline budgeted cost

  5. 0
    Jerome Soriano ·

    @ haresh, planned performance

    @ haresh,

    planned performance % complete @ any given date (data date) is the schedule % complete.

    so what you are looking for is exactly the "schedule % complete".

    you can check in your schedule that schedule % complete = planned value cost/baseline budgeted cost

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?