How can I change the resource type after resource assigning

Ayman EleishMember for 15 years 9 months
Created
2
2
0

Hi all,

When I exported project from p3,the resource type that assigned to the resources in P6 are not satisfactory,so I'd like to change the type of resources.

Is it possible by exporting to excel.

Thanks.

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hi Ayman,P3 does not knwo

    Hi Ayman,

    P3 does not knwo what a resource type is; therefore all your resources coming from a P3 project should be "labor"

    if you have access to the resource sheet in P6 (you maybe should have admin rights to do so), it is easy to change the resource type, at least between "labor" and "nonlabor"; going to "material " is less easy

    Alexandre

  2. 0
    Jingjun Zou ·

    Maybe the "Global Change" can

    Maybe the "Global Change" can changed the resource type.