Resource Histogram Units

Mohamed JamanMember for 15 years 9 months
Created
1
2
0

 

Dear All,
 
Primavera P6
 
"While creating Resource Histogram by Using Resource Usage Profile (Resource Histogram), The X-axis is Time Scale (by Default) But Y-axis is coming in Hours (h) , i need it in "Numbers" 
 
Say Example,
 
im generating Resource Histogram for Resource " Brick " it is already a "material" type Resource having unit of measure " Numbers " This i created thro Admin Categories ---> Unit of Measures
 
While generating Resource Histogram for brick material as i said above, it is coming for me in Y-axis unit is 'h' like 20h , 40h, 60h
 
 
i need this in Numbers like 20n, 40n, 60n or 20 No's , 40 No's , 60 No's like that
 
 
Need HELP !!!! MOST URGENT !!!!!!
 
 
Thanks in Advance

1 reply

Oldest first
  1. 0
    Dujin Kim ·

    You can not customize Y-axis

    You can not customize Y-axis in resource histogram.  P6 does not support.