Unresolved Mystery of timing in P6
- Created
- 4
- 1
I have a strange problem in my program. I have given a lag of 21 days. The predecessor activity is completing by
Dear All,
I have a strange problem in my program. The successor activity is starting on the same day, when predecessor activity is completing with FS, Zero days lag. For example Predecessor is completing on 15th August 2010 11:00 am , then the successor activity is starting on the same date i.e. by 15th August 2010 11:00 am.
I have crossed checked all the following and found to be correct:
- Start date and finish date.
- Data date time.
- Relationship lag calendar.
Pls give a proper advice to resolve this conflict.
regards,
Haresh Jayanth
4 replies