Completion date still a mystery
In the Open Standard
Haresh JayanthMember for 20 years 1 month
- Created
- 3
- 2
0
Dear Rodel,
I have tested my program in three different system. In 2 system i am getting the same completion date of 24th July 2011 , but in one system i am getting the completion date as 31st July 2011 , with -6 days float.
As per your earlier posting, i have changed the following:
a) Changed the default calendar.
b) Went to import - Change - Calendar from Keep Existing to Update existing.........
c) Match the working hours in all the 3 calendar same.
d) Made all the calculation changes , and any other changes same in these three systems.
But all my efforts have been failed, since in one system , i am getting a different completion date......
Any Good advice please....
regards,
Haresh Jayanth
I have tested my program in three different system. In 2 system i am getting the same completion date of 24th July 2011 , but in one system i am getting the completion date as 31st July 2011 , with -6 days float.
As per your earlier posting, i have changed the following:
a) Changed the default calendar.
b) Went to import - Change - Calendar from Keep Existing to Update existing.........
c) Match the working hours in all the 3 calendar same.
d) Made all the calculation changes , and any other changes same in these three systems.
But all my efforts have been failed, since in one system , i am getting a different completion date......
Any Good advice please....
regards,
Haresh Jayanth
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?