Dear Planners,

My currency as I assigned in the program is "x", however when I close my project and open another project later has a different currency, close this project and open my project, the currency is changed to the last one. This always happens in all settings like columns.

 

Regards,

 

Moutaz

2 replies

Oldest first
  1. 0
    Moutaz Aldeib ·

    Dear Planners, Is there any

    Dear Planners,

    Is there any help?

     

    Regards,

    Moutaz 

  2. 0
    Zoltan Palffy ·

    go to edit users

    go to edit users preference

    then select the Curreny tab and make your default currrency here