Level of Effort Percentage complete?

David SmithMember for 22 years 6 months
Created
1
2
0

Morning,

Have a few level of efforts in my current plan.  Haven't used them for a while and I am a little confused to how  the 'LOE' updates its percentage complete in relation to it's predecessors and successors.

I have one LOE with four activities tied into it, they all have Percentage complete type as 'pyhsical'.  each of these have varying amounts of % comp, but the LOE still remains at 0%.

 % comp can not be hand typed into a LOE, so how does one get this to calculate?

Many thanks in advance

 

Dave

1 reply

Oldest first
  1. 0
    Raymund de Laza ·

    Hi Dave, Physical percentage

    Hi Dave,

    Physical percentage will not roll up to the summary row. It will just show the physical percentage of individual activity. .

    Only Duration % Type will roll up to the summary.

     

    This is as per my experience.

     