Primavera ver 6.7 is not showing actual percentage why?
In the Open Standard
Irfan KhanMember for 17 years 3 months
- Created
- 1
- 2
0
Hi to all experts,
I am working with Primavera 6.7 version & I made a cost & resource loaded schedule.
My schedule’s percent completed type is = Physical & Duration Type is = Fixed Duration & Units.
But while updating the Percentage of schedule it is showing, Schedule % Complete = 22.28% &
Whenever I am transferring the same data to Primavera P3 it showing overall percentage = 4%.
Can anybody tell me why Primavera is not showing actual percentage as P3 shows.
Thanks,
1 reply