Primavera ver 6.7 is not showing actual percentage why?

Irfan KhanMember for 17 years 3 months
Created
1
2
0

Hi to all experts,

I am working with Primavera 6.7 version & I made a cost & resource loaded schedule.

My schedule’s percent completed type is = Physical & Duration Type is = Fixed Duration & Units.

But while updating the Percentage of schedule it is showing, Schedule % Complete = 22.28% &

Whenever I am transferring the same data to Primavera P3 it showing overall percentage = 4%.

Can anybody tell me why Primavera is not showing actual percentage as P3 shows.

Thanks,

1 reply

Oldest first
  1. 0
    Dieter Wambach ·

    Irfan Khan   The behaviour of

    Irfan Khan

     

    The behaviour of percent complete in P6 is different to P3.

    On your Primavera DVD there is a document "Moving From P3 to P6" (or similar). For a better understanding of the differences between P3 and P6 you can study the chapter "Autocost Rules". This will give the answer to your question.

    Hope this helps

    Regards Dieter