Resource Usage Profile Option - Unit Of Measure

Anbin PonnithMember for 17 years 4 months
Created
2
2
0

Hai

How can we Show in Resource Usage profile Option Unit of Measure As Nos.

I did it in Following Way

Eg I Created One Resource Carpenter  Resource Type - Labour Unit of Measure As - Nos

Edit-> User Preference ->Times->unit Format-> Day

After That I assigned the Carpenter to one Activity Type the Budget Unit as 40(Mandays)

I Clicked Resource Profile Option -> I selected Carpenter->Right Click Selected Resorce Profile Option-Data-> Display -> Unit->Selected Graph->Calculate Average->Divide Interval By->1, Unit of Measure -> Nos

But it is Not Showing

Can Anyone Say me where i am Wrong

When i Change Data->Display -> Cost it is Showing -> Unit of Measure as Nos

Regards

Anbin

 

 

 

 

 

2 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Hi. Go to User Preference >>

    Hi.

    Go to User Preference >> Time Units >> Check the check box for Show Unit Label.

     

    Raymund

  2. 0
    Khuong Do ·

    Hi.I write an article

    Hi.

    I write an article regarding Why is Unit of Measure not showing in Resource Usage Profile in Primavera P6.

    If you're interested, kindly read here https://doduykhuong.com/2017/07/31/why-is-unit-of-measure-not-showing-in-resource-usage-profile-in-primavera-p6/

Log in or join to reply