Schedulling Problem in Primavera v6.7
In the Open Standard
Faheem I.JanjuaMember for 15 years 9 months
- Created
- 0
- 3
0
Dear All,
I am facing a problem while scheduling in Primavera v6.7 as following:
- The start date of a successor activity is same as the end date of the predecessor activity.
- The start time of some activities is 7:00am which is the start of the day as set in the assigned project calendar, however some activities are starting at 11:00 am or 2:00pm.
- Total Float is coming not in whole numbers but in decimal figures.
Important thing to note is that I have set the Project Start time and the Calendar start time and the Schedule time same i.e., 7:00am but the problem still persists.
Can somebody help/advise me on this.
Thanks & Regards,
Faheem, PMP.
Project Planner
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?