Options while summarizing in P6

Krishna KumarMember for 19 years 8 months
Created
3
2
0

Hi Planners,

                 Kindly inform me if there is any options in P6 to show average date while summarizing the schedule & how can we hide the dates in the summarization sheet. Kindly help me ASAP.

 

Thank you

Krishna

3 replies

Oldest first
  1. 0
    Daniel Limson ·

    Krishna, In summary, P6

     

    Krishna,

    In summary, P6 will use the earliest start date and the latest finish date to calculate the total duration of the summary bar and it uses calendar days at 7 days per week.

    If you do not want to see the Start and Finish Dates , you can always remove the column.

     

    Best regards,

    Daniel

  2. 0
    Krishna Kumar ·

    Hi Daniel,

    Hi Daniel,

                 Thanks for your suggestion. And i've to clarify more that while summarize by groups upto level 4, i need to see dates on 2,3,4th level, but in my 1st level i've hide it. is it possible? i hope that you understand my question. Kindly give me your advice ASAP

    Thank you,

    Regards,

    Krishna

  3. 0
    Krishna Kumar ·

    Hi Daniel,

    Hi Daniel,

                 Thanks for your suggestion. And i've to clarify more that while summarize by groups upto level 4, i need to see dates on 2,3,4th level, but in my 1st level i've hide it. is it possible? i hope that you understand my question. Kindly give me your advice ASAP

    Thank you,

    Regards,

    Krishna