Depending on your particular software is how multi-resources can be edited. The following is from Spider Project Help Page.
Participants contains the list of resources comprising the current multi-resource. For each resource its name, code and units quantity in the multi-resource are displayed.
Quantity – sets the number of resource units in the multi-resource.
Add – lets the user add new resources to the multi-resource. Pressing Add button invokes the dialog box with a list of project resources. The user can select one or several desired resources from the list with the left mouse button and press OK. Note that: a resource cannot be added twice to one multi-resource.
Delete – removes selected resource from the current multi-resource composition.
Update content – enables the user to update the current multi-resource assignments globally in the project with new multi-resource properties and composition. Note that: historical project data cannot be updated, i.e. in the ongoing project with included performance data updating of multi-resources properties will not affect data before the project data date. The current multi-resource activity assignments are updated with the following peculiarities:
- Multi-resource assignments (quantity and composition of comprising resources) are not changed for completed activities.
- Multi-resource assignments (quantity and composition of comprising resources) are changed for uncompleted activities if resources comprising the current multi-resource have not actually participated in the activity execution. Otherwise, if resources have already been appointed to the activity, their composition and quantity assigned will be updated for further activity execution only (if the resource has been completely removed from the multi-resource, its name will still exist in the list of activities assignments with quantity equal to zero).
Multi resources is one functionality that perhaps do not add value to the resource leveling per-se as you can do the same with multiple individual resource assignments. But this is a functionality so convenient for resource loading is the one I use to load my crews as they move through many activities, it would be insane individually load the same crew on individual resource assigments to every activity, not to mention when several crews work on the same activity with different workload or partial assignment.
We do not change crew composition every other week as the crew moves to do work in other activities, modeling optimal crew composition for resource loading of each activity in our model would be misleading. Yes multi resources can be edited at the activity level but be careful of moving in the opposite direction of how crew composition will be managed on the site.
Best regards,
Rafael