Primavera P6 v.7 is not showing Unit of Measure ?

Irfan KhanMember for 17 years 3 months
Created
1
2
0

Hi to all,

Before i was using Primavera V6.2 than there was all Unit was available & right now i upgrade my Primavera from 6.2 to 6.7 here just these units are showing.

 

I dont know, where all old units gone expect below mentioned units. Please if anybody have idea so let me know.   

Unit Name                 Unit Abbreviation

Lump Sum                            LS

If                                          If

Linear Ft                               L ft

Hour                                      hr

Each                                     ea

Cubic yards                          cu yd

 

thanks.....

 

Irfan Khan

1 reply

Oldest first
  1. 0
    Andy Power ·

    Irfan You can add more units

    Irfan

    You can add more units of measure under Admin>Admin Categories and go to the unit of measure tab on the left hand side.

    Andy

Log in or join to reply