Copy Logic Between Projects
- Created
- 3
- 3
Hi,
This post relates to P6v7 SP2.
I want to know if you can change project id's on copied logic. i.e. move the logic from one programme (that is structurally the same (incl Act Ids) to another.
example:
I have 4 projects that make up a full programme in one EPS. These are logically linked from project to project (call it EPS group 1, PROJ1A, PROJ2A, PROJ3A, PROJ4A). If I make a copy of this group (call it EPS group 2 PROJ1B, PRO2B, PROJ3B, PROJ4B).
I then update PROJ1B , and replace PROJ1A (in eps group 1) with this (only between copied activities unchecked) . All The logic will be copied, but the project logic will be still be assinged the projects in EPS group 2, is there a way to reassign the project ids (on predecessors and successors) so the logic will link to the projects in EPS group 1??
I have also tried this in the WBS view, it doesnt work!
(if its a user setting this could be embarrassing)
Lets see if any of you Gurus can come up with an answer to this puzzle...good luck :-)
Brendan
3 replies
Oldest firstLog in or join to reply